The Port Colborne Record

Committee of Adjustment

August 14, 2024

What was decided (2 motions)

2 carried, 0 recorded otherwise. Every motion below is printed as the minutes print it.

That consent application B10-24-PC be granted subject to the following conditions: That the applicant provides the Secretary-Treasurer with the deeds in triplicate for the conveyance of the subject parcel or a registrable legal description of the subject parcel, together with a paper copy and electronic copy of the deposited reference plan, if applicable, for use in the issuance of the Certificate of Consent. That a final certification fee of $240 payable to the City of Port Colborne is submitted to the Secretary-Treasurer. That the owner enters into a Development Agreement with the City Port Colborne to implement the recommendations of the Revised Hydrogeological Assessment, prepared by Terra-Dynamics Consulting Inc. (dated June 7, 2024), for Part 1 and 2, prior to any construction or site alteration, to the satisfaction of the Niagara Region and City staff. That a drainage apportionment agreement be completed by the City's Drainage Superintendent or by an approved engineer at the cost of the applicant. A copy of the deposited plan must be delivered to the Drainage Superintendent through the planning department for the apportionment agreement to be completed. That Part 1 and Part 2 be provided with separate driveway entrances, to the satisfaction of City staff. That the applicant(s) sign the City of Port Colborne’s standard “Memorandum of Understanding” explaining that development charges and cash-in-lieu of the dedication of land for park purposes, based on an appraisal, at
Moved by A. Desmarais, seconded by Councillor G. Bruno
Carried
That consent application B10-24-PC be granted subject to the following conditions: 1. That the applicant provides the Secretary-Treasurer with the deeds in triplicate for the conveyance of the subject parcel or a registrable legal description of the subject parcel, together with a paper copy and electronic copy of the deposited reference plan, if applicable, for use in the issuance of the Certificate of Consent. 2. That a final certification fee of $240 payable to the City of Port Colborne is submitted to the Secretary-Treasurer. 3. That the owner enters into a Development Agreement with the City Port Colborne to implement the recommendations of the Revised Hydrogeological Assessment, prepared by Terra-Dynamics Consulting Inc. (dated June 7, 2024), for Part 1 and 2, prior to any construction or site alteration, to the satisfaction of the Niagara Region and City staff. 4. That a drainage apportionment agreement be completed by the City's Drainage Superintendent or by an approved engineer at the cost of the applicant. A copy of the deposited plan must be delivered to the Drainage Superintendent through the planning department for the apportionment agreement to be completed. 5. That Part 1 and Part 2 be provided with separate driveway entrances, to the satisfaction of City staff. 6. That the applicant(s) sign the City of Port Colborne’s standard “Memorandum of Understanding” explaining that development charges and cash-in-lieu of the dedication of land for park purposes, based o
Moved by A. Desmarais, seconded by Councillor G. Bruno
Carried

The town’s own record

Read the minutes this page was read from →

Where this page and that document disagree, the document is right and this record is wrong. Say so and it will be corrected.